CHG0032936 - 3rd party maintenance - LD5 Slough
Scheduled Maintenance Report for amatisnetworks
Completed
The scheduled maintenance has been completed.
Posted Oct 15, 2021 - 08:30 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 14, 2021 - 18:02 BST
Scheduled
One of our circuit providers will be carrying out fibre splicing in Slough LD5 area. This work should not impact any live services, but we will divert traffic away from our Slough LD5 to Reading Data Centre core link as a precaution.
This maintenance is also a risk to our Slough LD5 to Gloucester Exchange core link.

If any customers experience any issues during this time please raise to our Support team through the normal channels.
Posted Oct 11, 2021 - 13:24 BST
This scheduled maintenance affected: Core (Core Network Devices and Routing).