CHG0033108 - 3rd Party Maintenance - LD5

Scheduled Maintenance Report for amatisnetworks

Completed

The scheduled maintenance has been completed.
Posted Feb 01, 2022 - 06:00 GMT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 31, 2022 - 18:00 GMT

Scheduled

One of our circuit providers will be carrying out fibre splicing in Slough LD5 area. This work should not impact any live services, but we will divert traffic away from our Slough LD5 to Reading Data Centre core link as a precaution.
This maintenance is also a risk to our Slough LD5 to Gloucester Exchange core link.

If any customers experience any issues during this time please raise to our Support team through the normal channels.
Posted Jan 26, 2022 - 11:06 GMT
This scheduled maintenance affected: Core (Core Network Devices and Routing).