CHG0032915 - Hardware Upgrade - APEX Bracknell
Scheduled Maintenance Report for amatisnetworks
Completed
The scheduled maintenance has been completed.
Posted Oct 08, 2021 - 00:00 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 07, 2021 - 19:01 BST
Scheduled
amatis will be carrying out hardware upgrade in the APEX POP Bracknell exchange. Customers that terminate on this device will see a loss of service whilst the service is migrated on to the replacement device and have been notified directly.

Other traffic will be rerouted away from the device before the maintenance begins to prevent impact to other customer services. Some customer services may experience a slight increase in latency during the maintenance.
Posted Oct 04, 2021 - 08:40 BST
This scheduled maintenance affected: Connectivity (Ethernet Services (Fibre, EFM, GEA), xDSL Services (ADSL/FTTC)) and Core (Core Network Devices and Routing).